Memorandum

Date      December 1, 2016

TO           Boston Region Metropolitan Planning Organization

FROM     Karl H. Quackenbush, Executive Director

RE           Work Program for Freight Planning Support: FFY 2017

Action Required

Review and approval

Proposed Motion

That the Boston Region Metropolitan Planning Organization (MPO) vote to approve the work program for Freight Planning Support: FFY 2017, presented in this memorandum

Project Identification

Unified Planning Work Program Classification

Certification Requirements

CTPS Project Number

11145

Client

Boston Region MPO

CTPS Project Supervisors

Principal: Mark Abbott

Manager: William S. Kuttner

Funding

MPO Planning Contract #95411


 

Impact on MPO Work

This is MPO work and will be carried out in conformance with the priorities established by the MPO.

Background

The Boston Region MPO established a formal freight planning program that began in federal fiscal year (FFY) 2014. The MPO anticipates that freight analysis within the framework of this multiyear program will be ongoing, given the importance of freight transportation and the unique challenges that comprehensive freight analysis entails.

The goals of the program are as follows:

Prior to the inception of the program, the MPO directed its staff to develop an action plan that would further the MPO’s freight planning goals. The action plan was presented to the Boston Region MPO’s board on September 12, 2013 by MPO staff member William Kuttner and documented in his memorandum titled, “Proposed Freight Planning Action Plan for the Boston Region MPO: Meeting the Goals and Addressing the Issues.”The memorandum proposed several studies that would inform one or more of the MPO’s goals. As envisioned, the studies would be ongoing multiyear efforts and the analyses and recommendations from them would be far-reaching, possibly considering areas outside the Boston region.

Among the subjects recommended for study were truck traffic and related logistic issues, such as types of cargoes, in Everett, Chelsea, and the South Boston waterfront. The plan also recommended evaluating the adequacy of rest area locations for truckers in and near the Boston Region MPO area. These studies were undertaken in FFYs 2014, 2015 and 2016.

Other recommended study topics included dedicated truck routes, hazardous cargoes, and substandard interchanges, but publications for these remaining topics have not been prepared. Instead, important information related to hazardous cargoes and dedicated truck routes was obtained during the studies in Everett, Chelsea, and South Boston, and information on substandard interchanges was developed in freight analyses conducted in support of ongoing project evaluation work related to the MPO’s Long Range Transportation Plan (LRTP) and Transportation Improvement Program (TIP).

The Boston Region MPO freight program will now move into a new phase. The acquisition of regional truck flow data has been ongoing and these data are now available for improving the MPO’s regional travel demand model. In FFY 2017, the MPO staff proposed organizing these data and using them to develop maps of the underlying industrial geography and road network capabilities of the region.

Objectives

The principal objectives of this work program are as follows:

  1. Coordinate MPO planning efforts with regional freight stakeholders
  2. Examine the impact restrictions—specifically cargo limitations and weight and height restrictions—have on truck travel in the region and identify what, if  any, corridors or geographies have the potential to be improved by projects funded through the TIP process
  3. Continue developing region-wide freight flow data for trucking and other modes, and configure these data for use in travel demand model development

Work Description

Task 1  Coordinate MPO Efforts with Freight Stakeholders and Neighboring MPOs

The MPO staff will maintain an ongoing, collaborative relationship with the freight stakeholders who are affected by freight movement in the Boston Region MPO area. Some of the activities of this work program will involve MPO staff members attending and making presentations at meetings and conferences, some of which will be sponsored by the MPO. Recruiting regional freight stakeholders and encouraging them to be involved in activities of the MPO and its committees will also be a valuable part of outreach activities.

The rest area location study that was completed in FFY 2016, the proposed mapping of the region’s industrial geography, and the ongoing gathering of freight flow data all relate explicitly to MPOs which border on the Boston Region MPO’s planning area. Joint efforts to work with neighboring MPOs on these or other freight issues will be proposed whenever practical. The MPO staff anticipates that some follow-up efforts relating to truck rest area locations may be requested by regional stakeholders.

Task 2  Analysis of Truck Route Restrictions

Using geographic information system (GIS) resources and input from municipalities in the Boston Region MPO area, the MPO staff will create a spatial database for eastern Massachusetts of roadways that have restrictions based on vehicle type, size, and height that will limit the routes available to the trucking industry in their daily operations. 

The data from this exercise will be examined and used to help identify corridors or geographies that restrict or limit the amount of truck access. Some of these roadways might be ripe for improvement and may lend themselves as candidates for TIP projects that redesign and/or upgrade the infrastructure. 

This information will be used to help prioritize investment strategies that may improve truck routings and flows through the region, while taking into account local policy concerns and restrictions based on roadway safety, roadway functional class, and land use type. Safety restrictions, for example, prohibit hazardous cargo from tunnels; roadway functional class matters because of the desire to keep big trucks on interstates if possible; and land use is considered because of local concerns about keeping truck traffic out of residential areas whenever possible.

Products of Task 2

Task 3  Develop Additional Freight Data Sources

Data collection efforts in the Everett, Chelsea, and South Boston waterfront studies were designed to provide useful data for making improvements to the Boston Region MPO’s regional travel demand model. Further truck volume data collection is still ongoing. A task in the FFY 2017 work program will develop some of this data specifically for the purpose of model improvement.

Early in FFY 2017, toll booths on the western part of Interstate 90 were replaced by an all-electronic tolling system. Drivers no longer stop at toll booths to collect tickets and pay tolls. Vehicles now pass under gantries which can read vehicle transponders or capture license plate images for later billing. This new tolling system will be an important source for new data.

Products of Task 3

Estimated Schedule

It is estimated that this project will be completed 10 months after work commences. The proposed schedule, by task, is shown in Exhibit 1.

Estimated Cost

The total cost of this project is estimated to be $51,200. This includes the cost of 14.8 person-weeks of staff time, overhead at the rate of 102.70 percent, and travel direct costs. A detailed breakdown of estimated costs is presented in Exhibit 2.

KQ/WSK/wsk

Exhibit 1
ESTIMATED SCHEDULE
Freight Planning Support: FFY 2017


Task
Month
1 2 3 4 5 6 7 8 9 10
1.
Coordinate MPO Efforts with Freight Stakeholders and Neighboring MPOs
From month 1 to 11.
2.
Analysis of Truck Route Restrictions
From month 1 to 10.
Deliverable
A
, Technical memorandum delivered by Month 10
3.
Develop Additional Freight Data Sources
From month 3 to 11.
Deliverable
B
, Technical memorandum delivered by Month 11
Products/Milestones
A: Technical memorandum
B: Technical memorandum

 

 

Exhibit 2
ESTIMATED COST
Freight Planning Support: FFY 2017

Direct Salary and Overhead

$51,027

Task
Person-Weeks Direct
Salary
Overhead
(102.70%)
Total
Cost
M-1 P-5 P-4 Total
1.
Coordinate MPO Efforts with Freight Stakeholders and Neighboring MPOs
0.0 1.5 0.0 1.5 $2,789 $2,864 $5,652
2.
Analysis of Truck Route Restrictions
1.3 6.0 4.5 11.8 $19,597 $20,126 $39,722
3.
Develop Additional Freight Data Sources
0.0 1.5 0.0 1.5 $2,789 $2,864 $5,652
Total
1.3 9.0 4.5 14.8 $25,174 $25,853 $51,027

Other Direct Costs

$173
Travel
$173

TOTAL COST

$51,200
Funding
MPO Planning Contract #95411