TIP ID | Proponent(s) | Project Name | TIP/ LRTP Status | Estimated Cost | Design Status | Total Rating (154 Points Possible): | System Preservation, Modernization, and Efficiency Rating (36 Points Possible): | Livability and Economic Benefit Rating (29 Points Possible): | Mobility Rating (25 Points Possible): | Environment and Climate Change Rating (25 Points Possible): | Environmental Justice Rating (10 Points Possible): | Safety and Security Rating (29 Points Possible): |
---|---|---|---|---|---|---|---|---|---|---|---|---|
606635 | Newton & Needham | Reconstruction of Highland Avenue, Needham Street & Charles River Bridge, from Webster Street to Route 9 | LRTP 2021-25 | $21,390,000 | PRC Approved | 102 | 30 | 15 | 13 | 18 | 6 | 20 |
600220 | Beverly | Reconstruction & Signal Improvements on Rantoul Street (Route 1A), from Cabot Street (South) to Cabot Street (North) | 2014 | $15,143,095 | 25% Submitted | 98 | 28 | 18 | 15 | 18 | 0 | 19 |
606284 | Boston | Improvements to Commonwealth Avenue, from Amory Street to Alcorn Street | 2015 | $11,507,814 | 25% Approved | 96 | 28 | 16 | 15 | 9 | 8 | 20 |
606320 | Boston | Reconstruction of Causeway Street (Pedestrian & Bicycle Improvements) | $12,075,000 | 25% Submitted | 92 | 32 | 20 | 12 | 6 | 7 | 15 | |
605034 | Natick | Reconstruction of Route 27 (North Main Street), from North Avenue to the Wayland Town Line | $12,987,353 | 25% Submitted | 86 | 32 | 16 | 14 | 9 | 0 | 15 | |
605146 | Salem | Reconstruction on Canal Street, from Washington Street & Mill Street to Loring Avenue & Jefferson Avenue | 2014 | $6,059,201 | 25% Approved | 85 | 22 | 16 | 12 | 10 | 6 | 19 |
605313 | Natick | Bridge Replacement, Route 27 (North Main St.) over Route 9 (Worcester St.) and Interchange Improvements | $18,501,571 | 25% Submitted | 84 | 34 | 12 | 15 | 8 | 0 | 15 | |
605110 | Brookline | Intersection & Signal Improvements at Route 9 & Village Square (Gateway East) | 2016 | $4,970,387 | 25% Submitted | 84 | 30 | 19 | 14 | 10 | 0 | 11 |
029492 | Bedford, Billerica, & Burlington | Middlesex Turnpike Improvements, from Crosby Drive North to Manning Road (Phase III) | 2016 | $18,800,000 | 75% Submitted | 83 | 28 | 9 | 18 | 13 | 3 | 12 |
604810 | Marlborough | Reconstruction of Route 85 (Maple Street) | 2016 | $4,798,560 | 25% Submitted | 82 | 16 | 14 | 10 | 18 | 6 | 18 |
605657 | Medway | Reconstruction on Route 109, from Holliston Street to 100 Feet West of Highland Street | 2016 | $9,987,731 | 25% Submitted | 82 | 28 | 13 | 10 | 16 | 0 | 15 |
606460 | Boston | Improvements at Audubon Circle | $4,920,000 | 25% Submitted | 78 | 24 | 14 | 11 | 9 | 7 | 13 | |
601553 | Melrose | Intersection & Signal Improvement to Lebanon Street, from Lynde Street to Main Street | 2014 | $4,259,412 | 100% Approved | 77 | 26 | 12 | 13 | 11 | 0 | 15 |
605189 | Concord | Bruce Freeman Rail Trail, Phase 2C | LRTP 2021-25 | $6,260,080 | 25% Submitted | 77 | 24 | 14 | 10 | 14 | 2 | 13 |
602261 | Walpole (MassDOT) | Reconstruction on Route 1A (Main Street), from the Norwood Town Line to Route 27 | $11,500,000 | 25% Submitted | 76 | 28 | 14 | 10 | 6 | 6 | 12 | |
604652 | Winchester, Stoneham, & Woburn | Tri-Community Bikeway | 2015 | $5,019,517 | 75% Submitted | 75 | 20 | 15 | 9 | 17 | 0 | 14 |
605729 | Quincy | Intersection & Signal Improvements at Hancock Street & East/West Squantum Streets | 2014 | $3,908,598 | 100% Submitted | 74 | 24 | 11 | 10 | 7 | 5 | 17 |
604532 | Acton, Carlisle, & Westford | Bruce Freeman Rail Trail, Phase 2A | 2014 | $11,090,009 | 75% Submitted | 71 | 24 | 14 | 8 | 10 | 2 | 13 |
604935 | Woburn | Reconstruction of Montvale Avenue, from I-93 Interchange to Central Street | LRTP 2016-20 | $3,617,248 | 25% Submitted | 71 | 26 | 10 | 9 | 8 | 0 | 18 |
601704 | Newton | Reconstruction & Signal Improvements on Walnut Street, from Homer Street to Route 9 | $3,815,600 | 25% Submitted | 70 | 24 | 16 | 8 | 7 | 0 | 15 | |
601513 | Saugus (MassDOT) | Interchange Reconstruction at Walnut Street & Route 1 (Phase II) | $18,612,130 | 75% Approved | 69 | 22 | 12 | 15 | 7 | 0 | 13 | |
602077 | Lynn | Reconstruction on Route 129 (Lynnfield Street), from Great Woods Road to Wyoma Square | $3,457,578 | 25% Approved | 69 | 20 | 8 | 11 | 9 | 5 | 16 | |
604989 | Southborough | Reconstruction of Main Street (Route 30), from Sears Road to Park Street | $4,000,000 | 25% Submitted | 69 | 22 | 13 | 12 | 7 | 0 | 15 | |
602310 | Danvers | Reconstruction on Collins Street, from Sylvan Street to Centre & Holten Streets | $6,229,213 | 75% Approved | 68 | 20 | 13 | 14 | 6 | 2 | 13 | |
601579 | Wayland | Signal & Intersection Improvements at Route 27 (Main Street) and Route 30 (Commonwealth Road) | 2016 | $1,833,904 | 25% Submitted | 66 | 24 | 8 | 8 | 12 | 0 | 14 |
604531 | Acton & Maynard | Assabet River Rail Trail | LRTP 2016-20 | $7,300,000 | 25% Submitted | 66 | 16 | 14 | 10 | 13 | 0 | 13 |
604377 | Gloucester | Washington Street and Railroad Avenue | $4,289,989 | 25% Submitted | 65 | 12 | 15 | 9 | 8 | 4 | 17 | |
604231 | Marlborough | Intersection & Signal Improvements on Route 20 (East Main Street/Boston Post Road) at Concord Road | $1,706,600 | 25% Submitted | 64 | 24 | 4 | 16 | 7 | 3 | 10 | |
607258 | Quincy | Intersection Improvements at Quincy Avenue & East Howard Street | $1,487,430 | 25% Submitted | 64 | 18 | 7 | 8 | 12 | 5 | 14 | |
601705 | Reading | Reconstruction of West Street, from Woburn City Line to Summer Ave/Willow Street | $7,176,119 | 75% Submitted | 63 | 24 | 10 | 11 | 6 | 0 | 12 | |
601019 | Winchester | Signal & Improvements at 4 Locations on Church Street & Route 3 (Cambridge Street) | 2014 | $1,320,000 | 100% Submitted | 62 | 18 | 9 | 11 | 17 | 0 | 7 |
604996 | Woburn | Bridge Replacement, New Boston Street over MBTA | LRTP 2016-20 | $7,896,853 | 25% Submitted | 62 | 12 | 19 | 11 | 13 | 0 | 7 |
606117 | Boston | Traffic Signal Improvements at 9 Locations | $3,367,500 | 25% Submitted | 60 | 16 | 11 | 8 | 7 | 5 | 13 | |
605721 | Weymouth | Intersection Improvements at Middle Street, Libbey Industrial Parkway and Tara Drive | $937,326 | 25% Approved | 60 | 20 | 9 | 16 | 4 | 0 | 11 | |
600518 | Hingham (MassDOT) | Intersection Improvements at Derby Street, Whiting Street (Route 53) and Gardner Street | $1,582,468 | 25% Submitted | 59 | 22 | 10 | 13 | 2 | 0 | 12 | |
602000 | Weston | Intersection & Signal Improvements at Route 30 (South Ave) & Wellesley Street | $1,969,962 | 75% Submitted | 58 | 18 | 5 | 12 | 12 | 0 | 11 | |
606002 | Duxbury | Signal Installation at Route 3 (NB & SB) Ramps & Route 3A (Tremont St) | $2,400,000 | PRC Approved | 57 | 20 | 4 | 17 | 3 | 0 | 13 | |
604923 | Swampscott | Reconstruction of Humphrey Street and Salem Street | $2,404,552 | 25% Submitted | 57 | 6 | 17 | 9 | 10 | 0 | 15 | |
602602 | Hanover (MassDOT) | Reconstruction of Washington Street (Route 53) and Related Work From the Route 3 Northbound Ramp to Webster Street (Route 123) | 2014 | $983,381 | 25% Submitted | 56 | 20 | 9 | 11 | 7 | 0 | 9 |
603739 | Wrentham | Construction of I-495/Route 1A Ramps | $4,002,192 | 25% Submitted | 55 | 18 | 1 | 15 | 10 | 0 | 11 | |
604697 | Marlborough | Reconstruction of Farm Road, from Cook Lane to Route 20 (Boston Post Road) | $3,674,838 | 100% Submitted | 55 | 20 | 7 | 6 | 8 | 3 | 11 | |
605857 | Norwood | Intersection Improvements at Route 1 & University Avenue/Everett Street | $3,780,000 | PRC Approved | 54 | 22 | 8 | 12 | 3 | 0 | 9 | |
606130 | Norwood | Intersection Improvements at Route 1A & Upland Road/Washington Street & Prospect Street/Fulton Street | $3,275,390 | 25% Submitted | 53 | 20 | 5 | 10 | 5 | 0 | 13 | |
606316 | Brookline | Pedestrian Bridge Rehabilitation over MBTA off Carlton Street | $1,776,396 | 25% Submitted | 53 | 10 | 7 | 8 | 11 | 5 | 12 | |
604638 | Danvers & Peabody (MassDOT) | Mainline Improvements on Route 128 (Phase II) | $23,776,000 | 100% Approved | 47 | 12 | 1 | 18 | 3 | 0 | 13 | |
605743 | Ipswich | Resurfacing & Related Work on Central & South Main Streets | $2,603,060 | 25% Submitted | 47 | 6 | 13 | 8 | 6 | 0 | 14 | |
601359 | Franklin | Reconstruction of Pleasant Street, from Main Street to Chestnut Street | $5,378,680 | 75% Submitted | 45 | 12 | 11 | 6 | 4 | 0 | 12 | |
601607 | Hull | Reconstruction of Atlantic Avenue and Related Work, from Nantasket Avenue to Cohasset Town Line | $5,175,277 | 25% Submitted | 43 | 6 | 11 | 2 | 8 | 0 | 16 | |
604811 | Marlborough | Reconstruction of Route 20 (East Main Street), from Main Street Easterly to Lincoln Street | $2,252,930 | 75% Submitted | 42 | 6 | 4 | 11 | 7 | 3 | 11 | |
603462 | Duxbury (MassDOT) | Intersection Improvements at Kingstown Way (Route 53) & Winter Street | 2014 | $1,448,081 | 100% Submitted | 40 | 10 | 4 | 11 | 4 | 0 | 11 |
604745 | Wrentham | Reconstruction of Taunton Street (Route 152) | $3,945,871 | 25% Submitted | 36 | 6 | 10 | 2 | 4 | 0 | 14 |
TIP ID | Proponent() | Project Name | TIP/ LRTP Status | Estimated Cost | Design Status |
---|---|---|---|---|---|
604761 | Boston | Multi-Use Trail Construction (South Bay Harbor) From Ruggles Station to Fort Point Channel | 2014 | $4,108,636 | 100% Submitted |
605789 | Bostons | Reconstruction of Melnea Cass Boulevard | 2014 | $9,229,785 | PRC Approved |
606134 | Boston | Traffic Signal Improvements on Blue Hill Avenue and Warren Street | 2014 | $2,700,000 | PRC Approved |
602984 | Concord & Lincoln | Limited Access Highway Improvements at Route 2 & 2A, Between Crosby's Corner & Bedford Road | 2013-2014 | $51,828,136 | Under Construction |
604655 | Marshfield (MassDOT) | Bridge Replacement, Beach Street over the Cut River | 2015 | $2,243,522 | PRC Approved |
603711 | Needham & Wellesley (MassDOT) | Rehab/Replacement of 6 Bridges on I-95/Route 128 (Add-a-Lane Contract 5) | 2013-16 | $131,670,310 | 75% Submitted |
N/A | Somerville & Medford | Green Line Extension Project (Phase II), Medford Hillside (College Avenue) to Mystic Valley Parkway/Route 16 | 2016 | $190,100,000 | N/A |
601630 | Weymouth (MassDOT) | Reconstruction & Widening on Route 18 (Main Street), from Highland Place to Route 139 | 2013-2015 | $36,700,705 | 25% Submitted |
TIP ID | Proponent(s) | Project Name | TIP/ LRTP Status | Estimated Cost | Design Status |
---|---|---|---|---|---|
604123 | Ashland | Reconstruction on Route 126 (Pond Street), from the Framingham T.L. to the Holliston T.L. | $7,000,000 | PRC Approved | |
604369 | Beverly | Reconstruction & Improvements on Route 128 (Interchange 19) at Brimbal Avenue, Sohier Road, Dunham Road, Otis Road | $13,800,000 | PRC Approved | |
601274 | Boston | Reconstruction of Tremont Street, from Court Street to Boylston Street | $2,681,260 | 25% Submitted | |
053001 | Boston | Northern Avenue Connector Roads (Phase 1) | N/A | Conceptual | |
606226 | Boston | Reconstruction of Rutherford Avenue, from City Square to Sullivan Square | LRTP 2016-20 | $94,000,000 | PRC Approved |
606453 | Boston | Improvements on Boylston Street, from Intersection of Brookline Avenue & Park Drive to Ipswich Street | $6,555,000 | PRC Approved | |
900 | Canton | East-West Connector, between Pleasant St. & Route 138 | N/A | Conceptual | |
603883 | Canton | Reconstruction on Route 138, from I-93 to Dan Road | $2,850,000 | PRC Approved | |
87790 | Canton, Dedham, Norwood & Westwood (MassDOT) | Interchange Improvements at I-95/I-93 (University Avenue, Dedham Street) | LRTP 2021-25 | $224,250,000 | PRC Approved |
606146 | Canton, Norwood & Westwood | Ramp Construction on I-95 (NB) & Improvements on Dedham Street | LRTP 2021-25 | $35,000,000 | 75% Submitted |
1063 | Chelsea | Beacham and Williams Street | N/A | Conceptual | |
1443 | Chelsea | Broadway Reconstruction | N/A | Conceptual | |
953 | Chelsea | Spruce Street | N/A | Conceptual | |
1441 | Concord | Route 62 (Main St) Phase 3 | N/A | Conceptual | |
1450 | Concord | Route 117 (Fitchburg Turnpike) | N/A | Conceptual | |
602091 | Concord | Improvements & Upgrades to Concord Rotary (Routes 2/2A/119) | $98,900,000 | PRC Approved | |
606223 | Concord, Acton | Bruce Freeman Rail Trail Construction, Phase II-B | $5,760,000 | PRC Approved | |
600650 | Duxbury | Route 3A (Tremont Street) Bridge | N/A | Conceptual | |
942 | Duxbury | Intersection Improvements at Route 3A and Route 139 | N/A | Conceptual | |
1313 | Everett | Bike to the Sea/ Northern Strand Community Trail | N/A | Conceptual | |
649 | Everett & Malden | TeleCom Boulevard, Phase 2 | N/A | Conceptual | |
955 | Framingham | Route 126 (Route 9 to Lincoln Street) | N/A | Conceptual | |
602038 | Framingham | Edgell Road Corridor Project | $1,500,000 | PRC Approved | |
606109 | Framingham | Intersection Improvements at Route 126/135/MBTA & CSX Railroad | LRTP 2026-30 | $115,000,000 | PRC Approved |
1546 | Hingham | Derby Street Corridor Improvements | $4,200,000 | Conceptual | |
602260 | Holbrook | Abington Avenue-Plymouth Street | N/A | Conceptual | |
606501 | Holbrook | Reconstruction of Union Street (Route 139), from Linfield Street to Centre Street/Water Street | $1,368,000 | PRC Approved | |
607255 | Holbrook | Intersection Improvements and Related Work at Weymouth Street/Pine Street/Sycamore Street | $1,000,000 | PRC Approved | |
602929 | Holliston | Multi-Use Trail Construction on a Section of the Upper Charles Trail (2 Miles of Proposed 27 Miles) | $2,168,360 | 75% Submitted (2001) | |
1006 | Hopkinton | School Street/W. Main Street Intersections | N/A | Conceptual | |
606043 | Hopkinton | Signal & Intersection Improvements on Route 135 | $4,800,000 | PRC Approved | |
1047 | Hudson | South Street | N/A | Conceptual | |
1488 | Hudson | Lincoln St. at Cox St. and Packard St. | N/A | Conceptual | |
601906 | Hudson (MassDOT) | Bridge Replacement, Cox Street over the Assabet River | $1,000,000 | PRC Approved | |
603345 | Hudson & Marlborough (MassDOT) | Reconstruction on Routes I-290 & 495 and Bridge Replacement | $23,000,000 | PRC Approved | |
1139 | Hudson & Stow | Assabet River Rail Trail (through Stow) | N/A | Conceptual | |
1141 | Lexington | West Lexington Greenway | N/A | Conceptual | |
1157 | Lexington | East Mass Ave Intersections | N/A | Conceptual | |
604619 | Lexington | Route 4/225 (Bedford Street) and Hartwell Avenue | $15,687,000 | Conceptual | |
1319 | Lynn | Route 129 (Boston St./Washington St.) | N/A | Conceptual | |
1320 | Lynn | Route 1 (Copeland Circle, Fox Hill Bridge) | N/A | Conceptual | |
1321 | Lynn | Route 1A Lynnway at Blossom Street | N/A | Conceptual | |
1322 | Lynn | Route 1A Lynnway intersection at Market St. | N/A | Conceptual | |
1323 | Lynn | Route 1A Lynn (GE Bridge Nahant Rotary) | N/A | Conceptual | |
1324 | Lynn | Blue Line Extension (Wonderland Connection) | N/A | Conceptual | |
1454 | Lynn | Route 1 South (Jug handle lights at Goodwin Circle) | N/A | Conceptual | |
601138 | Lynn | Traffic Signals at 4 Locations (Contract E) | $435,000 | PRC Approved | |
602081 | Lynn | Route 107 (Western Avenue)/ Eastern Avenue | N/A | PRC Approved | |
602093 | Lynn | Route 107 (Western Avenue) | N/A | PRC Approved | |
943 | Lynn | Broad Street/Lewis Street /Route 129 | N/A | Conceptual | |
944 | Lynn | Boston Street - Hamilton Street | N/A | Conceptual | |
374 | Lynn | Lynn Garage | N/A | Conceptual | |
351 | Lynn, Malden, Revere & Saugus | Bike to the Sea, Phase 2 | N/A | Conceptual | |
1454 | Lynnfield, Lynn & Peabody | Route 1 South (Jug handle lights at Goodwin Circle) | N/A | Conceptual | |
605012 | Malden, Revere & Saugus (MassDOT) | Reconstruction & Widening on Route 1, from Route 60 to Route 99 | LRTP 2031-35 | $172,500,000 | PRC Approved |
605664 | Marshfield (MassDOT) | Resurfacing & Related Work on Route 3A | $2,643,371 | 75% Submitted | |
1458 | Medford | Mystic River Linear Park | N/A | Conceptual | |
1146 | Medford | Medford Square Parking | N/A | Conceptual | |
1455 | Medford | Medford Square Phase 2 Improvements | N/A | Conceptual | |
1456 | Medford | Medford Square Water Taxi Landing and related Park Improvements | N/A | Conceptual | |
1457 | Medford | Medford Square Transit Center | N/A | Conceptual | |
1167 | Medway | Route 109 (Milford Street) | N/A | Conceptual | |
602134 | Medway | Resurfacing & Related Work on a Section of Village Street | $1,824,000 | PRC Approved | |
601551 | Melrose | Intersection & Signal Improvements at Main Street & Essex Street | $1,884,000 | PRC Approved | |
967 | Milford | Veteran's Memorial Drive/Alternate Route | N/A | Conceptual | |
602364 | Millis | Reconstruction of Village Street, from Main Street (Route 109) to the Medway Town Line | $6,900,000 | PRC Approved | |
1066 | Natick | Cochituate Rail Trail, Phase Two | N/A | Conceptual | |
607312 | Natick | Superstructure Replacement, Marion Street over MBTA | $2,358,000 | PRC Approved | |
1067 | Newton | Washington St., Phase 2 | N/A | Conceptual | |
600932 | Newton | Reconstruction on Route 30 (Commonwealth Avenue), from Weston Town Line to Auburn Street | $2,208,000 | PRC Approved | |
1451 | Quincy | Quincy Center Multimodal MBTA Station | N/A | Conceptual | |
005399 | Salem | Reconstruction of Bridge Street, from Flint Street to Washington Street | LRTP 2016-20 | $11,223,250 | 25% Submitted (2004) |
1311 | Salem | Canal Street Bikeway | N/A | Conceptual | |
600986 | Salem | Boston Street | N/A | PRC Approved | |
1461 | Somerville | Community Path (Phase 3) - Lowell to Lechmere | N/A | Conceptual | |
600831 | Somerville (MassDOT) | I-93 Mystic Avenue Interchange (Design and Study) | N/A | PRC Approved | |
1064 | Southborough | Cordaville Road/Route 85 Rehabilitation | N/A | Conceptual | |
1037 | Sudbury | Route 20/Horsepond Road | N/A | Conceptual | |
1069 | Sudbury | Route 20/Wayside Inn Road | N/A | Conceptual | |
1164 | Sudbury | Bruce Freeman Rail Trail, Phase 2D | N/A | Conceptual | |
1305 | Sudbury | Bruce Freeman Rail Trail, Phase 2E | N/A | Conceptual | |
971 | Sudbury | Old Sudbury Road (Route 27) | N/A | Conceptual | |
607249 | Sudbury | Route 20/Landham Road Intersection | N/A | Conceptual | |
997 | Walpole | Coney Street Interchange with Route 95 | N/A | Conceptual | |
1151 | Walpole | Walpole Central Business District | N/A | Conceptual | |
1152 | Walpole | Elm St Improvements | N/A | Conceptual | |
600671 | Walpole (MassDOT) | Reconstruction of Route 1A, from Common Street to the Norfolk Town Line | N/A | 25% Submitted (2000) | |
1153 | Woburn | Woburn Loop Bikeway Project | N/A | Conceptual | |
1449 | Woburn | Route 38 (Main St.) Traffic Lights | N/A | Conceptual | |
950 | Woburn | South Bedford Street | N/A | Conceptual |