Memorandum
Date January 23, 2014
TO Boston Region Metropolitan Planning Organization
FROM Karl H. Quackenbush
CTPS Executive Director
RE Work Program for: Freight Planning Support – FFY 2014
Review and approval
That the Boston Region Metropolitan Planning Organization vote to approve the work program for Freight Planning Support – FFY 2014, presented in this memorandum.
Technical Support/Operations Analysis Projects
11145
Boston Metropolitan Planning Organization
Principal: Efi Pagitsas
Manager: William S. Kuttner
MPO Planning Contract #78890
MPO §5303 Contract #78922
This is MPO work and will be carried out in conformance with the priorities established by the MPO.
Recognizing the importance of freight transportation and the unique challenges that a comprehensive freight analysis entails, the Boston Region Metropolitan Planning Organization (MPO) established a formal freight-planning program that began in federal fiscal year (FFY) 2014. The MPO anticipates that freight analysis within the framework of this multiyear program will be ongoing.
To this end, staff was directed in FFY 2013 to develop an “action plan” for this program that would further the MPO’s freight-planning goals. These goals can be summarized as follows:
The memorandum dated September 12, 2103, “Proposed Freight Planning Action Plan for the Boston Region MPO: Meeting the Goals and Addressing the Issues,”presented a group of possible studies that would address one or more of these goals and were within the capabilities of MPO staff. These study options are far-reaching and envision an ongoing multiyear effort.
It is necessary, however, to select one or more study topics as a place to start. The work program proposed here focuses on the importance and challenges of the Beacham Street corridor and the surrounding areas in Everett and Chelsea. This subject is an attractive starting point for several reasons:
The program also envisions that some data gathering and analysis not directly related to the Beacham Street corridor will also be undertaken. These additional efforts will fill in some gaps in our understanding of regional logistics or serve as exploratory work to better define future MPO freight-planning work programs.
The principal objectives of this work program are:
Freight and associated land use issues will be identified in consultation with local planning officials and other stakeholders. An existing-conditions profile will be developed utilizing existing studies, field observation, and interviews with local industries and businesses. Prospective development and evolving land use patterns will be identified as important aspects of the existing conditions.
Additional issues in the study area may be identified during the preparation of the existing-conditions profile. Also, related regional connectivity issues outside the study will be identified and analyzed as resources permit.
In consultation with local planning officials and other stakeholders MPO staff will develop one or more planning options that can be evaluated.
Planning-level alternatives to be evaluated
A preliminary evaluation of the selected planning options will be performed. The strengths and deficiencies of the evaluated options will be identified. Viable options and associated implementation strategies may be recommended, as well as suggestions for more detailed follow-on analysis.
Technical memorandum with recommendations and supporting data and analysis.
It is estimated that this project will be completed eight months after work commences. The proposed schedule, by task, is shown in Exhibit 1.
The total cost of this project is estimated to be $33,787. This includes the cost of 12.2 person-weeks of staff time and overhead at the rate of 97.42 percent. A detailed breakdown of estimated costs is presented in Exhibit 2.
KQ/WSK/wsk
Task |
Month | |||||||
---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
1.
Identify Issues and Develop Existing-Conditions Profile |
From month 1 to 5.
| |||||||
2.
Develop Options Addressing Identified Issues |
From month 4 to 6.
| |||||||
3.
Evaluate Selected Planning Options |
From month 4 to 9.
Deliverable A, Technical memorandum delivered by Month 9
|
Task |
Person-Weeks | Direct Salary |
Overhead (97.42%) |
Total Cost |
||||
---|---|---|---|---|---|---|---|---|
M-1 | P-5 | P-2 | SP-1 | Total | ||||
1.
Identify Issues and Develop Existing-Conditions Profile
|
0.0 | 2.2 | 0.0 | 2.0 | 4.2 | $5,062 | $4,931 | $9,992 |
2.
Develop Options Addressing Identified Issues
|
0.2 | 1.0 | 0.0 | 0.0 | 1.2 | $2,033 | $1,980 | $4,013 |
3.
Evaluate Selected Planning Options
|
1.7 | 3.2 | 1.9 | 0.0 | 6.8 | $10,020 | $9,761 | $19,781 |
Total
|
1.9 | 6.4 | 1.9 | 2.0 | 12.2 | $17,114 | $16,673 | $33,787 |