Boston Region MPO Staff Recommendation:

FFY 2015 Unified Planning Work Program (UPWP) New Discrete Projects                       (Revised May 15, 2014)

 

This staff recommendation reflects consideration of factors including MPO visions and policies (as documented in Paths to a Sustainable Region, the MPO's long-range transportation plan); federal guidance; national goals and planning factors;  contributions to a balanced mix of modes in the region; geographic equity; UPWP Committee member priorities; and other regional priorities.

 

 

MPO Staff-Recommended Proposed Projects
ID Proposed Project Name Proposed Project Group Estimated Total Cost Estimated Share of FHWA PL Funds Estimated FHWA PL Funds Estimated FTA Section 5303 Funds Notes    LRTP Vision Topic: Climate Change    LRTP Vision Topic:  Environment    LRTP Vision Topic:  Livability     LRTP Vision Topic: Mobility      LRTP Vision Topic: Regional Equity      LRTP Vision Topic: Safety and Security      LRTP Vision Topic: System Preservation, Modernization, and Efficiency   Project Function: MPO Planning Project Function:  Support to Regional Transportation Stakeholders Project Function: Contribution to Transportation Knowledge UPWP Focus Area: Link Land Use and Transportation UPWP Focus Area: Work with Limited Financial Resources  UPWP Focus Area: Use a Management and Operations Approach UPWP Focus Area: Protect Air Quality and the Environment UPWP Focus Area: Increase Transit and Healthy-Transportation Mode Share UPWP Focus Area: Encourage Sustainable Communities and Livability UPWP Focus Area: Advance Mobility and Access,
  and Reduce Congestion
  UPWP Focus Area: Improve System Reliability  UPWP Focus Area: Increase Transportation Safety and Security   UPWP Focus Area: Support Economic Vitality UPWP Focus Area: Preserve and Maintain the Transportation System UPWP Focus Area: Consider Transportation Equity  and Accessibility UPWP Focus Area: Support MetroFuture Implementation UPWP Focus Area: Support Statewide and Regional Transportation Initiatives   UPWP Focus Area: Enhance Technical Knowledge, Capacity, and Insights     UPWP Focus Area: Support Performance-Based Planning
A-1 Addressing Safety, Mobility, and Access on Subregional Priority Roadways: FFY 2015 Roadway Network Performance $110,000 60% $66,000 $44,000 The proposed funding for this recommended project has been reduced in response to MPO staff's receipt of FFY 2015 FHWA PL and FTA Section 5303 fund allocations for the Boston Region MPO. Not Applicable Applicable Applicable Applicable Not Applicable Applicable Applicable Not Applicable Applicable Not Applicable Secondary Consideration Secondary Consideration Primary Consideration Secondary Consideration Secondary Consideration Secondary Consideration Primary Consideration Secondary Consideration Primary Consideration Secondary Consideration Primary Consideration Not Applicable Primary Consideration Primary Consideration Not Applicable Not Applicable
A-2 Low-Cost Improvements to Bottleneck Locations: FFY 2015 Roadway Network Performance $40,000 100% $40,000 $0 None Not Applicable Not Applicable Not Applicable Applicable Not Applicable Not Applicable Applicable Not Applicable Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Secondary Consideration Not Applicable Not Applicable Primary Consideration Secondary Consideration Secondary Consideration Secondary Consideration Secondary Consideration Not Applicable Not Applicable Primary Consideration Not Applicable Not Applicable
A-3 Priority Corridors for LRTP Needs Assessment: FFY 2015 Roadway Network Performance $110,000 60% $66,000 $44,000 The proposed funding for this recommended project has been reduced in response to MPO staff's receipt of FFY 2015 FHWA PL and FTA Section 5303 fund allocations for the Boston Region MPO. Not Applicable Applicable Not Applicable Applicable Not Applicable Applicable Applicable Applicable Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Secondary Consideration Secondary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Primary Consideration  Not Applicable Not Applicable
B-2 Bicycle Network Gaps: Feasibility Evaluations Active Transportation $55,000 100% $55,000 $0 None Not Applicable Not Applicable Applicable Applicable Not Applicable Applicable Not Applicable Not Applicable Applicable Not Applicable Not Applicable Secondary Consideration Not Applicable Secondary Consideration Primary Consideration Secondary Consideration Primary Consideration  Not Applicable Secondary Consideration Not Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Not Applicable Not Applicable
B-3 Community Pedestrian Network Studies  Active Transportation $40,000 100% $40,000 $0 None Not Applicable Not Applicable Applicable Applicable Not Applicable Applicable Applicable Not Applicable Applicable Not Applicable Secondary Consideration Secondary Consideration Not Applicable Not Applicable Primary Consideration Secondary Consideration Primary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Secondary Consideration Primary Consideration Primary Consideration Secondary Consideration Secondary Consideration
C-1  Safety Analysis at Intersections near MAGIC Schools Safety and Security $22,250 65% $14,400 $7,850 MPO staff would undertake a portion of the proposed project scope, which would include several elements of the base-mapping activities, at this funding level. The MPO might consider pursuing further analysis of student commuting patterns as part of a future UPWP. The proposed funding for this recommended project has been reduced in response to MPO staff's receipt of FFY 2015 FHWA PL and FTA Section 5303 fund allocations for the Boston Region MPO. Not Applicable Not Applicable Applicable Applicable Not Applicable Applicable Not Applicable Not Applicable Applicable Not Applicable Secondary Consideration Primary Consideration Primary Consideration Not Applicable Secondary Consideration Primary Consideration Primary Consideration Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Secondary Consideration Not Applicable
D-2 Title VI Service Equity Analyses: Methodology Development Transportation Equity and Accessibility $55,000 0% $0 $55,000 None Not Applicable Not Applicable Not Applicable Applicable Applicable Not Applicable Not Applicable Applicable Applicable Applicable Not Applicable Not Applicable Not Applicable Not Applicable Secondary Consideration Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Not Applicable Primary Consideration Primary Consideration Primary Consideration
E-1 Core Capacity Constraints Land Use, Environment, and Economy $120,000 68% $50,000 $70,000 None Not Applicable Not Applicable Applicable Applicable Not Applicable Not Applicable Applicable Not Applicable Applicable Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Primary Consideration Not Applicable Not Applicable Secondary Consideration Primary Consideration Not Applicable Secondary Consideration Primary Consideration Secondary Consideration Not Applicable
G-1 Household-Survey-Based Travel Profiles and Trends: Selected Policy Topics Other Technical Support $75,000 53% $40,000 $35,000 The proposed funding for this recommended project has been reduced in response to MPO staff's receipt of FFY 2015 FHWA PL and FTA Section 5303 fund allocations for the Boston Region MPO. Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Applicable Not Applicable Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Primary Consideration Secondary Consideration
blank Total Cost of Staff-Recommended Proposed Projects blank $627,250 blank $371,400 $255,850 blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank

 

 

 

MPO Staff-Recommended Projects Funding Summary
Funding Category Estimated Total Funds Estimated FHWA PL Funds Estimated FTA Section 5303 Funds Notes 
Total Funding Available for New Discrete Projects $627,250 $371,400 $255,850 These funding levels are based on FFY 2015 FHWA PL and FTA 5303 allocations to the Boston Region MPO and estimated costs for ongoing and continuing work included in the draft proposed FFY 2015 UPWP budget. 
Total Cost of Staff-Recommended Proposed Projects $627,250 $371,400 $255,850 blank
Balance of Available Funding $0 $0 $0  

 

 

 

Projects Not Included in MPO Staff-Recommended Proposed Projects
ID Proposed Project Name Name Proposed Project Group Estimated Total Cost Estimated Share of FHWA PL Funds Estimated FHWA PL Funds Estimated FTA 5303 Funds Notes    LRTP Vision Topic: Climate Change    LRTP Vision Topic:  Environment    LRTP Vision Topic:  Livability     LRTP Vision Topic: Mobility      LRTP Vision Topic: Regional Equity      LRTP Vision Topic: Safety and Security      LRTP Vision Topic: System Preservation, Modernization, and Efficiency   Project Function: MPO Planning Project Function:  Support to Regional Transportation Stakeholders Project Function: Contribution to Transportation Knowledge UPWP Focus Area: Link Land Use and Transportation UPWP Focus Area: Work with Limited Financial Resources  UPWP Focus Area: Use a Management and Operations Approach UPWP Focus Area: Protect Air Quality and the Environment UPWP Focus Area: Increase Transit and Healthy-Transportation Mode Share UPWP Focus Area: Encourage Sustainable Communities and Livability UPWP Focus Area: Advance Mobility and Access,
  and Reduce Congestion
  UPWP Focus Area: Improve System Reliability  UPWP Focus Area: Increase Transportation Safety
  and Security
  UPWP Focus Area: Support Economic Vitality UPWP Focus Area: Preserve and Maintain the Transportation System UPWP Focus Area: Consider Transportation Equity  and Accessibility UPWP Focus Area: Support MetroFuture Implementation UPWP Focus Area: Support Statewide and Regional Transportation Initiatives   UPWP Focus Area: Enhance Technical Knowledge, Capacity, and Insights     UPWP Focus Area: Support Performance-Based Planning
F-1 Evaluation of Information-Technology-Based Programs for Encouraging Mode Shift Transit $55,000 70% $38,500 $16,500 MPO staff propose to explore this topic as part of the Greenhouse Gas Reduction Strategy Alternatives: Cost Effectiveness Analysis, which is currently underway. Not Applicable  Not Applicable  Applicable Applicable Not Applicable  Not Applicable  Not Applicable  Not Applicable  Not Applicable  Applicable Not Applicable Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Not Applicable
D-1 Community and Human-Services Transportation Support Transportation Equity and Accessibility $45,000 0% $0 $45,000 This proposed project was removed from the list of MPO staff-recommended projects in response to MPO staff's receipt of FFY 2015 FHWA PL and FTA Section 5303 fund allocations for the Boston Region MPO. Not Applicable Not Applicable Applicable Applicable Applicable Not Applicable Not Applicable Not Applicable Applicable Applicable Not Applicable Primary Consideration Secondary Consideration Not Applicable Primary Consideration Secondary Consideration Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Primary Consideration Primary Consideration Not Applicable
F-3 Universal Unlimited Transit Pass / EcoPass Program Feasibility Study Transit $55,000 0% $0 $55,000 None Not Applicable  Not Applicable  Applicable Applicable Not Applicable  Not Applicable  Not Applicable  Not Applicable  Applicable Applicable Not Applicable Primary Consideration Not Applicable Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Primary Consideration Primary Consideration Not Applicable
F-2 Non-Fixed-Route Transportation Services: Lessons for Transit Agencies Transit $55,000 0% $0 $55,000 None Not Applicable  Not Applicable  Applicable Applicable Applicable Not Applicable  Not Applicable  Not Applicable  Applicable Applicable Not Applicable Secondary Consideration Secondary Consideration Not Applicable Primary Consideration Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Secondary Consideration Primary Consideration Primary Consideration Not Applicable
F-4 Hudson / Marlborough Suburban Mobility Study  Transit $35,000 0% $0 $35,000 None Not Applicable  Not Applicable  Applicable Applicable Applicable Not Applicable  Not Applicable  Not Applicable  Applicable Not Applicable  Secondary Consideration Not Applicable Not Applicable Secondary Consideration Primary Consideration Secondary Consideration Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Secondary Consideration Not Applicable Not Applicable
E-2 Watertown: Development Impacts on Transportation  Land Use, Environment, and Economy $55,000 70% $38,500 $16,500 None Not Applicable  Not Applicable  Applicable Applicable Not Applicable  Not Applicable  Applicable Not Applicable  Applicable Not Applicable  Primary Consideration Not Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Primary Consideration Not Applicable Not Applicable Secondary Consideration Primary Consideration Not Applicable Secondary Consideration Primary Consideration Not Applicable Not Applicable
G-3 MPO Independent Staff Research and Idea Development Other Technical Support $35,000 70% $24,500 $10,500 None Not Applicable  Not Applicable  Not Applicable  Not Applicable  Not Applicable  Not Applicable  Not Applicable  Applicable Not Applicable  Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Secondary Consideration
B-1 Regional Bicycle Crash Self-Reporting Survey Active Transportation $55,000 70% $38,500 $16,500 None Not Applicable  Not Applicable  Not Applicable  Not Applicable  Not Applicable  Applicable Not Applicable  Applicable Applicable Applicable Not Applicable Not Applicable Not Applicable Not Applicable Primary Consideration Secondary Consideration Not Applicable Not Applicable Primary Consideration Not Applicable Not Applicable Not Applicable Secondary Consideration Primary Consideration Primary Consideration Primary Consideration
G-2 Public Health and Transportation Data Exploration Other Technical Support $55,000 70% $38,500 $16,500 None Not Applicable  Not Applicable  Applicable Not Applicable  Not Applicable  Not Applicable  Not Applicable  Applicable Not Applicable  Applicable Not Applicable Not Applicable Not Applicable Not Applicable Secondary Consideration Primary Consideration Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Not Applicable Secondary Consideration Secondary Consideration Primary Consideration Secondary Consideration
B-4 Fairmount Line Station Access Analysis (added May 15, 2014) Active Transportation $75,000 70% $52,500 $22,500       Applicable Applicable   Applicable     Applicable         Secondary Consideration Primary Consideration Secondary Consideration Primary Consideration   Primary Consideration   Secondary Consideration Secondary Consideration Primary Consideration Primary Consideration    
blank Total Cost for Non-Staff-Recommended Projects  blank $520,000 blank $231,000 $289,000 blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank blank