Proponent(s) | Project Name | Project Cost | AADT | Safety | System Preservation | Capacity Management/Mobility (Autos) | Capacity Management/Mobility (Buses) | Capacity Management/Mobility (Peds/Bikes) | Economic Vitality | Total Rating | 5 or more low ratings | 4 or more low ratings | 3 or more low ratings | 2 or more low ratings | 2 or more high ratings | 3 or more high ratings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Boston | Replacement of Allston I-90 Elevated Viaduct (B-16-359, MM 131.0-131.5, STR 111), including Interchange Reconstruction Beacon Park Yard Layover, and West Station | $460,000,000 | 174,000 | 2 | 3 | 2 | 2 | 3 | 3 | 15 | X | X | ||||
Weymouth (MassDOT) | Reconstruction & Widening on Route 18 (Main Street), from Highland Place to Route 139 | $58,822,115 | 29,600 | 3 | 3 | 2 | 1 | 2 | 3 | 14 | X | X | ||||
Newton & Needham | Reconstruction of Highland Avenue, Needham Street & Charles River Bridge, from Webster Street to Route 9 | $14,297,606 | 35,000 | 3 | 3 | 2 | 1 | 2 | 3 | 14 | X | X | ||||
Lexington | Route 4/225 (Bedford Street) and Hartwell Avenue | $15,687,000 | 40,200 | 3 | 2 | 2 | 2 | 3 | 2 | 14 | X | |||||
Boston | Reconstruction of Rutherford Avenue, from City Square to Sullivan Square | $109,967,000 | 48,200 | 2 | 3 | 1 | 1 | 3 | 3 | 13 | X | X | X | |||
Somerville | McGrath Boulevard Project | $65,000,000 | 38,000 | 2 | 3 | 1 | 1 | 3 | 3 | 13 | X | X | X | |||
Somerville & Woburn | Extend I-93 HOV Lane into Somerville and/or Capacity Improvements to Route 128, Woburn | $550,000,000 | 202,000 | 1 | 3 | 3 | 3 | 1 | 2 | 13 | X | X | X | X | ||
Reading, Stoneham, Wakefield, Woburn (MassDOT) | Interchange Improvements to I-93/I-95 (Bridge Replacement and Related Work |
$294,000,000 | 373,000 | 3 | 2 | 3 | 2 | 1 | 2 | 13 | X | |||||
Natick | Bridge Replacement, Route 27 (North Main St.) over Route 9 (Worcester St.) and Interchange Improvements | $25,793,370 | 80,000 | 3 | 3 | 2 | 2 | 2 | 1 | 13 | X | |||||
Woburn | Bridge Replacement, New Boston Street over MBTA | $9,706,549 | 14,000 | 1 | 1 | 3 | 1 | 3 | 3 | 12 | X | X | X | X | ||
Malden, Revere, Saugus (MassDOT) | Reconstruction & Widening on Route 1, from Route 60 to Route 99 | $236,078,161 | 115,000 | 2 | 1 | 3 | 3 | 1 | 2 | 12 | X | X | ||||
Braintree | I-93/Route 3 Interchange (Braintree Split) | $53,288,794 | 282,000 | 3 | 2 | 3 | 2 | 1 | 1 | 12 | X | X | ||||
Woburn | Reconstruction of Montvale Avenue, from I-93 Interchange to Central Street | $4,225,256 | 31,000 | 3 | 3 | 2 | 1 | 2 | 1 | 12 | X | X | ||||
MassDOT | Southeast Expressway Modification (Southampton Interchange) | $143,750,000 | 225,000 | 2 | 2 | 2 | 2 | 2 | 2 | 12 | X | |||||
Canton, Dedham, Norwood & Westwood | Interchange Improvements at I-95/I-93/University Avenue/I-95 Widening | $190,000,000 | 240,000 | 2 | 2 | 2 | 1 | 2 | 3 | 12 | ||||||
Needham & Wellesley | Rehab/Replacement of 6 Bridges on I-95/Route 128 (Add-a-Lane Contract 5) | $150,000,000 | 188,000 | 2 | 3 | 3 | 1 | 1 | 1 | 11 | X | X | X | |||
Concord | Improvements & Upgrades to Concord Rotary (Routes 2/2A/119) | $98,900,000 | 48,000 | 2 | 3 | 3 | 1 | 1 | 1 | 11 | X | X | X | |||
Canton, Norwood & Westwood | Ramp Construction on I-95 (NB) & Improvements on Dedham Street, Includes Replacement of 4 Signalized Intersections | $50,961,567 | 5,000 | 1 | 1 | 3 | 1 | 2 | 3 | 11 | X | X | X | |||
MassDOT | Route 3 South Express Toll Lanes | $800,000,000 | 159,000 | 3 | 3 | 2 | 1 | 1 | 1 | 11 | X | X | X | X | ||
Hopkinton, Westborough (MassDOT) | Reconstruction of I-90/I-495 Interchange | $220,000,000 | 209,000 | 2 | 3 | 2 | 1 | 1 | 2 | 11 | X | X | ||||
Bedford, Billerica, & Burlington | Middlesex Turnpike Improvements, from Crosby Drive North to Manning Road (Phase III) | $26,935,171 | 14,300 | 2 | 3 | 1 | 1 | 2 | 2 | 11 | X | X | ||||
Framingham | Intersection Improvements at Route 126/135/MBTA & CSX Railroad | $115,000,000 | 35,400 | 2 | 1 | 1 | 2 | 2 | 3 | 11 | ||||||
Reading, Stoneham, Wakefield | Improvements along Route 128/95, from North of Interchange of Interchange 37 to Interchange 40, including Modifications to Interchange 38 | $32,900,000 | 164,000 | 2 | 2 | 2 | 1 | 1 | 2 | 10 | X | |||||
Revere (MassDOT) | Mahoney Circle Grade Separation | $60,000,000 | 56,000 | 1 | 1 | 2 | 3 | 1 | 2 | 10 | X | X | ||||
Southborough, Westborough (MassDOT) | Improvements on Route 9 at I-495 Interchange, from Computer Drive/Research Drive to Route 9/Crystal Road Intersection | $25,000,000 | 135,000 | 1 | 3 | 2 | 1 | 1 | 2 | 10 | X | X | ||||
Danvers & Peabody (MassDOT) | Mainline Improvements on Route 128 (Phase II) | $23,776,000 | 102,000 | 2 | 3 | 2 | 1 | 1 | 1 | 10 | X | X | ||||
Boston | Boardman Street at Route 1A | $13,686,000 | 59,500 | 1 | 1 | 3 | 2 | 1 | 2 | 10 | X | X | ||||
Saugus (MassDOT) | Interchange Reconstruction at Walnut Street & Route 1 (Phase II) | $19,500,000 | 136,000 | 2 | 1 | 2 | 1 | 2 | 1 | 9 | X | X | ||||
Salem | Reconstruction of Bridge Street, from Flint Street to Washington Street | $16,613,152 | 17,800 | 2 | 2 | 1 | 1 | 1 | 2 | 9 | X | X | ||||
Chelsea & Revere | Route 1/Route 16 Connector | N/A | 40,200 | 1 | 3 | 1 | 1 | 1 | 2 | 9 | X | X | X | |||
Lynnfield & Reading | I-95 Capacity Improvements, Lynnfield to Reading (used old LRTP project Beverly to Peabody) | $198,443,000 | 157,000 | 1 | 1 | 3 | 1 | 1 | 2 | 9 | X | X | X | |||
Hudson & Marlborough | Reconstruction on Routes I-290 & 495 and Bridge Replacement | $100,000,000 | 162,500 | 2 | 3 | 1 | 1 | 1 | 1 | 9 | X | X | X | |||
Revere | Route 1A/Route 16 Connector | N/A | 36,700 | 1 | 2 | 1 | 1 | 1 | 2 | 8 | X | X | X | |||
Beverly | Interchange Reconstruction at Route 128/Exit 19 at Brimbal Avenue (Phase II) | $23,000,000 | 73,500 | 1 | 2 | 1 | 1 | 1 | 2 | 8 | X | X | X | |||
Newton | I-90/Interchange 17 | $4,000,000 | 141,000 | 2 | 1 | 2 | 1 | 1 | 1 | 8 | X | X | X | |||
Peabody | Route 128 Capacity Improvements: Exit 26 to Exit 28 | $24,634,000 | 110,000 | 1 | 1 | 3 | 1 | 1 | 1 | 8 | X | X | X | X | ||
Newton | New Route 128 Ramp to Riverside Station | N/A | 23,500 | 1 | 1 | 1 | 1 | 1 | 2 | 7 | X | X | X | X | ||
Woburn | Bridge Replacement & Related Work, W-43-028, Washington Street over I-95 | $13,557,856 | 38,800 | 1 | 1 | 1 | 1 | 2 | 1 | 7 | X | X | X | X | ||