FFYs 2026–2030 Transportation Improvement Program Readiness Scenario

 

Project ID Proponent(s) Project Name MPO Score MAPC
Subregion
Initial TIP Year and TIP FFYs 2025–29
Programmed Year(s)
FFYs 2026–30
Programmed
Year(s)
Design Status /
Date Last Update
Design Status (Shorthand) Last Update Date Years Since Last PINFO Milestone FFY 2025 FFY 2025 (New) FFY 2026 FFY 2026 (New) FFY 2027 FFY 2027 (New) FFY 2028 FFY 2028 (New) FFY 2029 FFY 2029
(New)
FFY 2030
(New)
Other Non-Target Funds FFYs 2026–30
Target Program Spending
Adjusted TFPC
 (FFYs 2025-29)
Adjusted TFPC
 (FFYs 2026-30)
S12807 MWRTA MWRTA CATCHCONNECT MICTROTRANSIT EXPANSION PHASE 2 – FRAMINGHAM AND NATICK EXTENDED HOURS 90 MWRC 2024
(FFYs 2024–28)
2024-26 2024-26 N/A N/A N/A N/A $165,625 $165,625 $162,500 $162,500 $0 $0 $0 $0 $0 $0 $0 $0 $162,500 $380,477 $380,477
609531 MassDOT ARLINGTON- STRATTON SCHOOL IMPROVEMENTS (SRTS) N/A ICC 2025
(FFYs 2025–29)
2025 2025 PS&E Received - Resubmission 3 (1/27/2025) PS&E 1/27/25 0.05 $2,305,605 $2,305,605 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $2,314,320 $2,314,320
609211 Peabody PEABODY- INDEPENDENCE GREENWAY EXTENSION 34 NSTF 2024
(FFYs 2020–24)
2025 2025 PS&E Received - Resubmission 2 (5/31/2024) PS&E 5/31/24 0.71 $8,273,695 $8,273,695 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $8,273,695 $8,273,695
608051 MassDOT RECONSTRUCTION ON ROUTE 38 (MAIN STREET), FROM ROUTE 62 TO THE WOBURN CITY LINE 59 NSPC 2023
(FFYs 2020–24)
2025 2025 100% Received (1/19/2024) 100% 1/19/24 1.07 $37,452,645 $37,452,645 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $37,452,645 $37,452,645
S12970 CATA CATA - VEHICLE REPLACEMENT (4 VEHICLES) TBD NSTF 2025-26
(FFYs 2025–29)
2025-26 2025-26 N/A N/A N/A N/A $1,710,000 $1,710,000 $750,000 $750,000 $0 $0 $0 $0 $0 $0 $0 $0 $750,000 $2,460,000 $2,460,000
S12971 MWRTA MWRTA- BLANDIN HUB EQUITABLE REDESIGN INITIATIVE TBD MWRC 2025-26
(FFYs 2025–29)
2025-26 2025-26 N/A N/A N/A N/A $1,750,000 $1,750,000 $750,000 $750,000 $0 $0 $0 $0 $0 $0 $0 $0 $750,000 $2,500,000 $2,500,000
S12963 Chelsea, Revere CHELSEA-REVERE- REGIONAL ON DEMAND MICROTRANSIT PILOT PROJECT 53.75 ICC 2025
(FFYs 2025–29)
2025-27 2025-27 N/A N/A N/A N/A $499,649 $499,649 $450,278 $450,278 $463,807 $463,807 $0 $0 $0 $0 $0 $0 $1,413,734 $1,413,734 $1,413,375
610544 Peabody PEABODY- MULTI-USE PATH CONSTRUCTION OF INDEPENDENCE GREENWAY AT I-95 AND ROUTE 1 53 NSTF 2025
(FFYs 2021–25)
2025 2026 75% Received (9/12/2024) 75% 9/12/24 0.42 $13,966,099 $0 $0 $22,091,033 $0 $0 $0 $0 $0 $0 $0 $0 $22,091,033 $13,966,099 $22,091,033
611982 Medford MEDFORD- SHARED USE PATH CONNECTION AT THE ROUTE 28/WELLINGTON UNDERPASS N/A ICC 2025
(FFYs 2025–29)
2025 2026 100% Received (10/31/2024) 100% 10/31/24 0.29 $6,061,917 $0 $0 $5,488,945 $0 $0 $0 $0 $0 $0 $0 $0 $5,488,945 $606,917 $5,488,945
608067 MassDOT WOBURN- INTERSECTION RECONSTRUCTION AT ROUTE 3 (CAMBRIDGE ROAD) AND BEDFORD ROAD AND SOUTH BEDFORD STREET 52 NSPC 2025
(FFYs 2021–25)
2025 2026 25% Approved (1/22/2024) 25% 1/22/24 1.06 $3,438,311 $0 $0 $3,438,311 $0 $0 $0 $0 $0 $0 $0 $0 $3,438,311 $1,978,080 $3,438,311
S13147 Framingham FRAMINGHAM- PRELIMINARY DESIGN OF INTERSECTION IMPROVEMENTS AT ROUTE 126/135/MBTA AND CSX RAILROAD TBD MWRC 2026
(FFYs 2025–29)
2026 2026 N/A N/A N/A N/A $0 $0 $1,400,000 $1,400,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,400,000 $1,400,000 $1,400,000
S13146 Lexington LEXINGTON- DESIGN OF SAFETY IMPROVEMENTS AT THE INTERSTATE 95 AND ROUTE 4/225 INTERCHANGE TBD MAGIC 2026
(FFYs 2025–29)
2026 2026 N/A N/A N/A N/A $0 $0 $1,650,000 $1,650,000 $0 $0 $0 $0 $0 $0 $0 $0 $1,650,000 $1,650,000 $1,650,000
608940 Weston WESTON- INTERSECTION IMPROVEMENTS BOSTON POST ROAD (ROUTE 20) AT WELLESLEY STREET  50.6 MWRC 2026
(FFYs 2023–27)
2026 2026 100% Received (12/13/2024) 100% 12/13/24 0.17 $0 $0 $3,237,804 $4,125,249 $0 $0 $0 $0 $0 $0 $0 $0 $4,125,249 $3,237,804 $4,125,249
609204 Belmont BELMONT- COMMUNITY PATH, BELMONT COMPONENT OF THE MCRT (PHASE I) 64.6 ICC 2026
(FFYs 2023–27)
2026-27 2026 25% Received (1/5/2022) 25% 1/5/22 3.11 $0 $0 $8,000,000 $19,711,298 $12,499,750 $0 $0 $0 $0 $0 $0 $0 $19,711,298 $20,499,750 $19,711,298
606453 Boston BOSTON- IMPROVEMENTS ON BOYLSTON STREET, FROM INTERSECTION OF BROOKLINE AVENUE AND PARK DRIVE TO IPSWICH STREET 58 ICC 2019
(FFYs 2016–20)
2026 2027 25% Received - Resubmission 1 (1/29/2021) 25% 1/29/21 4.04 $0 $0 $8,665,052 $0 $0 $15,000,000 $0 $0 $0 $0 $0 $0 $15,000,000 $8,665,052 $15,000,000
609532 MassDOT CHELSEA- TARGETED SAFETY IMPROVEMENTS AND RELATED WORK ON BROADWAY, FROM WILLIAMS STREET TO CITY HALL AVENUE 83 ICC 2026
(FFYs 2024–28)
2026 2027 75% Comments to DE (4/1/2024) 75% 4/1/24 0.87 $0 $0 $9,807,515 $0 $0 $9,430,303 $0 $0 $0 $0 $0 $0 $9,430,303 $9,807,515 $9,430,303
605168 Hingham HINGHAM- IMPROVEMENTS ON ROUTE 3A FROM OTIS STREET/COLE ROAD  INCLUDING SUMMER STREET AND ROTARY; ROCKLAND STREET TO GEORGE WASHINGTON BOULEVARD 55 SSC 2024
(FFYs 2020–24)
2026 2027 75% Comments to DE (4/29/2024) 75% 4/29/24 0.79 $0 $0 $28,738,432 $0 $0 $33,227,512 $0 $0 $0 $0 $0 $0 $33,227,512 $28,738,432 $33,227,512
608045 MassDOT MILFORD- REHABILITATION ON ROUTE 16, FROM ROUTE 109 TO BEAVER STREET 43 SWAP 2024
(FFYs 2020–24)
2026 2027 25% Received - Resubmission 2 (10/13/2023) 25% 10/13/23 1.34 $0 $0 $13,548,565 $0 $0 $13,548,565 $0 $0 $0 $0 $0 $0 $13,548,565 $9,758,201 $13,548,565
610823 Quincy QUINCY- INTERSECTION IMPROVEMENTS AT WILLARD STREET AND RICCIUTI DRIVE 41.1 ICC 2026
(FFYs 2025–29)
2026 2027 75% Received - Resubmission 1 (6/12/2024) 75% 6/12/24 0.67 $0 $0 $1,885,353 $0 $0 $3,700,546 $0 $0 $0 $0 $0 $0 $3,700,546 $1,885,353 $3,700,546
609252 Lynn LYNN- REHABILITATION OF ESSEX STREET 66 ICC 2024
(FFYs 2020–24)
2026-27 2027 PRC Approved (12/6/2018) PRC 12/6/18 6.19 $0 $0 $10,000,000 $0 $9,698,640 $19,698,640 $0 $0 $0 $0 $0 $0 $19,698,640 $19,698,640 $19,698,640
605857 MassDOT NORWOOD- INTERSECTION IMPROVEMENTS AT ROUTE 1 AND UNIVERSITY AVENUE/EVERETT STREET  55 TRIC 2021
(FFYs 2017–21)
2026-27 2027 25% Received - Resubmission 1 (1/5/2021) 25% 1/5/21 4.11 $0 $0 $27,636,336 $0 $0 $27,636,336 $0 $0 $0 $0 $0 $0 $27,636,336 $28,699,272 $27,636,336
612989 Boston BOSTON- BRIDGE PRESERVATION, B-16-066 (38D), CAMBRIDGE STREET OVER MBTA 53.2 ICC 2026
(FFYs 2024–28)
2027 2027 PRC Approved (12/21/2022) PRC 12/21/22 2.15 $0 $0 $0 $0 $16,632,000 $17,167,572 $0 $0 $0 $0 $0 $0 $17,167,572 $16,632,000 $17,167,572
611983 Chelsea CHELSEA- PARK STREET AND PEARL STREET RECONSTRUCTION 69.9 ICC 2027
(FFYs 2023–27)
2027 2027 PRC Approved (1/28/2021) PRC 1/28/21 4.05 $0 $0 $0 $0 $11,287,647 $11,287,647 $0 $0 $0 $0 $0 $0 $11,287,647 $11,705,708 $11,705,708
609257 Everett EVERETT- RECONSTRUCTION OF BEACHAM STREET 54 ICC 2024
(FFYs 2020–24)
2027 2027 25% Comments to DE (5/8/2024) 25% 5/8/24 0.77 $0 $0 $0 $0 $12,539,448 $12,539,448 $0 $0 $0 $0 $0 $0 $12,539,448 $12,539,448 $12,539,448
609437 Salem SALEM- PEABODY- BOSTON STREET IMPROVEMENTS 68 NSTF 2026
(FFYs 2023–27)
2027 2027 75% Received (1/17/2024) 75% 1/17/24 1.08 $0 $0 $0 $0 $26,122,722 $26,122,722 $0 $0 $0 $0 $0 $0 $26,122,722 $26,122,722 $26,122,722
605743 Ipswich IPSWICH- RESURFACING AND RELATED WORK ON CENTRAL AND SOUTH MAIN STREETS 47 NSTF 2023
(FFYs 2019–23)
2027-28 2027-28 25% Received (7/12/2024) 25% 7/12/24 0.59 $0 $0 $0 $0 $6,000,000 $6,000,000 $5,728,698 $9,035,254 $0 $0 $0 $0 $15,035,254 $11,728,698 $15,035,254
607981 MassDOT SOMERVILLE- MCGRATH BOULEVARD CONSTRUCTION 72.2 ICC 2027
(FFYs 2023–27)
2027-31 2027-31 25% Received (10/21/2024) 25% 10/21/24 0.32 $0 $0 $0 $0 $30,000,000 $30,000,000 $30,000,000 $33,075,573 $30,310,000 $30,310,000 $35,000,000 $0 $128,385,573 $95,310,000 $128,385,573
608954 Weston WESTON- RECONSTRUCTION ON ROUTE 30 49.2 MWRC 2026
(FFYs 2023–27)
2027 2028 25% Design Public Hearing (9/22/2022) 25% 9/22/22 2.40 $0 $0 $0 $0 $19,999,712 $0 $0 $19,999,712 $0 $0 $0 $0 $19,999,712 $19,999,712 $19,999,712
608436 Ashland ASHLAND- REHABILITATION AND RAIL CROSSING IMPROVEMENTS ON CHERRY STREET 38 MWRC 2024
(FFYs 2020–24)
2028 2028 25% Comments to DE (8/19/2020) 25% 8/19/20 4.49 $0 $0 $0 $0 $0 $0 $1,316,340 $1,269,327 $0 $0 $0 $480,000 $1,269,327 $1,222,315 $1,269,327
610932 Brookline BROOKLINE- REHABILITATION OF WASHINGTON STREET 62.4 ICC 2027
(FFYs 2023–27)
2028 2028 PRC Approved (9/24/2020) PRC 9/24/20 4.39 $0 $0 $0 $0 $0 $0 $10,000,000 $28,995,267 $18,995,267 $0 $0 $0 $28,995,267 $28,995,267 $28,995,267
610691 Natick COCHITUATE RAIL TRAIL EXTENSION (MBTA STATION TO MECHANIC STREET) - NATICK CENTER CONNECTION 67 MWRC 2028
(FFYs 2024–28)
2028 2028 25% Received - Resubmission 1
(9/4/2024)
25% 9/4/24 0.44 $0 $0 $0 $0 $0 $0 $7,492,849 $11,496,322 $0 $0 $0 $0 $11,496,322 $7,760,451 $11,496,322
610666 Swampscott SWAMPSCOTT- RAIL TRAIL CONSTRUCTION 66.4 NSTF 2027
(FFYs 2023–27)
2028 2028 PRC Approved (12/19/2019) PRC 12/19/19 5.16 $0 $0 $0 $0 $0 $0 $8,624,000 $0 $0 $8,624,000 $0 $0 $8,624,000 $8,932,000 $8,624,000
610545 Wakefield WAKEFIELD- MAIN STREET RECONSTRUCTION 61.8 NSPC 2028
(FFYs 2024–28)
2028 2028 PRC Approved (12/19/2019) PRC 12/19/19 5.16 $0 $0 $0 $0 $0 $0 $18,435,976 $25,000,000 $0 $0 $0 $0 $25,000,000 $16,581,200 $18,435,976
608158 Westwood WESTWOOD- NORWOOD- RECONSTRUCTION OF CANTON STREET TO UNIVERSITY DRIVE, INCLUDING REHAB OF N-25-032=W-31-018 53.3 TRIC FFY 2028
(FFYs 2024–28)
2028-29 2028-29 25% Design Public Hearing (9/28/2023) 25% 9/28/23 1.38 $0 $0 $0 $0 $0 $0 $12,854,847 $12,854,847 $10,000,000 $10,000,000 $0 $0 $22,854,847 $22,854,847 $22,854,847
609246 Lynn LYNN- REHABILITATION OF WESTERN AVENUE (ROUTE 107) 74.9 ICC 2027
(FFYs 2023–27)
2028-31 2028-31 PRC Approved (12/6/2018) PRC 12/6/18 6.19 $0 $0 $0 $0 $0 $0 $15,000,000 $15,000,000 $20,000,000 $20,000,000 $10,897,600 $0 $45,897,600 $40,980,000 $45,897,600
613088 Malden MALDEN- SPOT POND BROOK GREENWAY 73 ICC 2027
(FFYs 2024–28)
2028 2029 PRC Approved (12/20/2022) PRC 12/20/22 2.15 $0 $0 $0 $0 $0 $0 $4,858,127 $0 $0 $4,858,127 $0 $0 $4,858,127 $4,858,127 $4,858,127
606226 Boston BOSTON- RECONSTRUCTION OF RUTHERFORD AVENUE, FROM CITY SQUARE TO SULLIVAN SQUARE 59 ICC 2020
(FFYs 2016–20)
2028-32 2029-33 25% Received - Resubmission 1 (10/5/2020) 25% 10/5/20 4.36 $0 $0 $0 $0 $0 $0 $33,500,000 $0 $45,000,000 $33,500,000 $33,500,000 $0 $67,000,000 $197,759,449 $197,759,449
613319 Sudbury SUDBURY-FRAMINGHAM- BIKE PATH CONSTRUCTION OF BRUCE FREEMAN RAIL TRAIL, FROM THE SUDBURY DIAMOND RAILROAD CROSSING TO EATON ROAD WEST 47 MAGIC 2029
(FFYs 2025–29)
2029 2029-30 25% Received (7/9/2024) 25% 7/9/24 0.60 $0 $0 $0 $0 $0 $0 $0 $0 $4,263,000 $8,628,506 $0 $0 $8,628,506 $8,526,000 $8,628,506
610662 Woburn WOBURN- ROADWAY AND INTERSECTION IMPROVEMENTS AT WOBURN COMMON, ROUTE 38 (MAIN STREET), WINN STREET, PLEASANT STREET, AND MONTVALE AVENUE 75 NSPC 2025
(FFYs 2021–25)
2029 2029 PRC Approved (12/19/2019) PRC 12/19/19 5.16 $0 $0 $0 $0 $0 $0 $0 $0 $9,335,200 $9,335,200 $8,691,200 $0 $18,026,400 $17,382,600 $18,670,200
612963 Bellingham BELLINGHAM- ROADWAY REHABILITATION OF ROUTE 126 (HARTFORD ROAD), FROM 800 FEET NORTH OF THE I-495 NB OFF RAMP TO MEDWAY TOWN LINE, INCLUDING B-06-017 54.3 SWAP 2029
(FFYs 2025–29)
2029 2029-30 PRC Approved (6/24/2024) PRC 6/24/24 0.64 $0 $0 $0 $0 $0 $0 $0 $0 $8,340,000 $8,340,000 $8,074,000 $0 $16,414,000 $16,680,000 $16,414,000
612738 Ipswich IPSWICH- ARGILLA ROAD ROADWAY RECONSTRUCTION 37.9 NSTF 2029
(FFYs 2025–29)
2029 2029-30 PRC Approved (5/12/2022) PRC 5/12/22 2.76 $0 $0 $0 $0 $0 $0 $0 $0 $3,000,000 $5,183,829 $0 $0 $5,183,829 $5,183,829 $5,183,829
S13145 CTPS PROJECT DESIGN SET-ASIDE N/A REGIONWIDE N/A N/A 2027-30 Administrative N/A N/A N/A $0 $0 $0 $0 $0 $2,000,000 $0 $3,000,000 $0 $3,000,000 $3,000,000 $0 $11,000,000 $0 $11,000,000
S12820 CTPS BIKESHARE STATE OF GOOD REPAIR SET-ASIDE N/A REGIONWIDE N/A 2026-29 2027-30 Administrative N/A N/A N/A $0 $0 $1,000,000 $0 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $0 $8,000,000 $6,000,000 $7,000,000
S12124 CTPS COMMUNITY CONNECTIONS PROGRAM N/A REGIONWIDE N/A 2026-29 2027-30 Administrative N/A N/A N/A $0 $0 $1,887,222 $0 $2,036,193 $2,036,193 $2,000,000 $2,000,000 $2,500,000 $2,500,000 $2,500,000 $0 $9,036,193 $8,334,827 $8,423,415
S12113 CTPS TRANSIT TRANSFORMATION PROGRAM N/A REGIONWIDE N/A 2026-29 2026-29 Administrative N/A N/A N/A $0 $0 $5,000,000 $0 $5,500,000 $5,500,000 $6,000,000 $6,000,000 $6,500,000 $6,500,000 $7,000,000 $0 $25,000,000 $21,500,000 $23,000,000

 

 

 

Federal Fiscal Year 2025 2025 (New) 2026 2026 (New) 2027 2027 (New) 2028 2028 (New) 2029 2029 (New) 2030 (New) 2026-30 Total
Total Available Regional Highway Target Funds (FFYs 2026-30 TIP): $128,427,689 $128,427,689 $125,285,688 $125,285,687 $155,132,143 $152,627,429 $158,052,175 $158,700,879 $161,030,608 $157,518,346 $160,037,411 $754,169,752
                         
Draft Total Programmed Regional Highway Target Funds: $0 $103,829,110 $121,056,279 $60,017,614 $154,316,112 $237,359,291 $157,810,837 $169,726,302 $160,243,467 $152,779,662 $110,662,800 $730,545,669
Regional Highway Target Funds Remaining (Unprogrammed): $128,427,689 $24,598,579 $4,229,409 $65,268,073 $816,031 -$84,731,862 $241,338 -$11,025,423 $787,141 $4,738,684 $49,374,611 $23,624,083
Percent Unprogrammed 100.0% 19.2% 3.4% 52.1% 0.5% -55.5% 0.2% -6.9% 0.5% 3.0% 30.9% 3.1%

 

 

Projects in red text are identified as being high risk for staying on schedule based on information obtained at the February 2025 TIP readiness meeting.

 

Projects in orange text were identified as candidates to remain on schedule if near-term issue resolution occurs.

 

Red, bolded text on cost figures indicates a change in project funding, either an increase in cost and/or a delayed start year.

 

Black, bolded text on project names indicates an administrative line item.  These line items often set aside funding to be allocated in future TIP cycles.  

 

Highlighting indicates a project was recommended to move out to a later TIP year.
Highlighting indicates a project is proposed to be added to the TIP.  

 

Abbreviations

TIP investment programs: BP = Bicycle and Pedestrian. CC = Community Connections. CS = Complete Streets. II = Intersection Improvements. MI = Major Infrastructure. TT = Transit Transformation.

Metropolitan Area Planning Council (MAPC) subregions: ICC = Inner Core Committee. MAGIC = Minuteman Advisory Group on Interlocal Coordination. MWRC = MetroWest Regional Collaborative. NSPC = North Suburban Planning Council. NSTF = North Shore Task Force. SSC = South Shore Coalition. SWAP = SouthWest Advisory Planning Committee. TRIC = Three Rivers Interlocal Council.

Other abbreviations: CATA = Cape Ann Transportation Authority. CTPS = Central Transportation Planning Staff. DE = Design Engineer. FFY = federal fiscal year. MAPC = Metropolitan Area Planning Council. MassDOT = Massachusetts Department of Transportation. MBTA = Massachusetts Bay Transportation Authority. MCRT = Massachusetts Central Rail Trail. MPO = Metropolitan Planning Organization. MWRTA = MetroWest Regional Transit Authority. N/A = not applicable. NB = northbound. PINFO = MassDOT Project Info. PRC = MassDOT's Project Review Committee. PS&E = Plans, Specifications, and Estimates. TBD = To Be Determined. TFPC = Total Federal Participating Cost.