Draft Memorandum for the Record

Boston Region Metropolitan Planning Organization
TIP Process, Engagement, and Readiness Committee Meeting Minutes

February 25, 2026, Meeting

3:00 PM–4:44 PM, Zoom Video Conferencing Platform

Jen Rowe, Chair, representing the City of Boston

Decisions

The Boston Region Metropolitan Planning Organization’s (MPO) TIP Process, Engagement, and Readiness Committee agreed to the following:

Materials

Materials for this meeting included the following:

1.     January 22, 2026, TIP Process, Engagement, and Readiness Meeting Minutes (pdf) (html)

Meeting Agenda

1.    Introductions

J. Rowe welcomed committee members to the TIP Process, Engagement, and Readiness Committee meeting. See attendance on page 12.

2.    Public Comments

Justin Curewitz (Tighe & Bond) commented regarding the two Lynn projects programmed in the FFYs 2026–30 TIP, the Rehabilitation of Western Ave (project ID 609246) and the Rehabilitation of Essex Street (project ID 609252). The Readiness Baseline published for the February 19, 2026, MPO board meeting programmed both of these projects in FFY 2030 in accordance with the MPO’s recently adopted readiness policy. J. Curewitz stated that advertising both projects in the same year would be a significant undertaking for the City of Lynn.  

3.    Action Item: Approval of January 22, 2026, Meeting Minutes

A motion to approve the minutes was made by the Inner Core Committee (Brad Rawson) and seconded by the Town of Brookline (Erin Chute). The motion carried.

4.    Federal Fiscal Years (FFY) 2027–31 TIP Project Updates and Readiness Guidelines—Ethan Lapointe, MPO Staff

E. Lapointe reviewed the discussion that took place during the MPO board meeting of February 19, 2026. MPO staff and board members discussed projects that are not on track to advertise before FFY 2031 based on the readiness guidelines, cost increases, and the trend of funding shifting away from municipal projects due to a lack of project readiness.

E. Lapointe stated that the MPO’s program projections made in January were too optimistic compared to the Readiness Baseline, because some projects that were scheduled to submit design packages did not. He noted that the projects that applied for funding for the FFYs 2027–31 TIP are generally well-aligned with MPO readiness guidelines. Only two of the eight projects do not have a pre-25 percent design submission, and four of the eight have a 25 percent submission. Several of these projects are at more advanced design states than currently funded projects. These may one day function as a “bench” of municipal proponent projects. A project “bench” includes projects at advanced design stages that can be programmed as fill-in projects in the inner years of the TIP if surplus funding becomes available. However, most of these projects have readiness years of FFY 2030 or 2031, so could not yet be programmed in the earlier years of the TIP.  

E. Lapointe stated that the Massachusetts Department of Transportation (MassDOT) and the MPO are working together to build a more secure TIP program. For example, during TIP Readiness Days, MassDOT incorporated the MPO’s readiness guidelines in its recommendations.

E. Lapointe described the five projects that have cost increases not yet incorporated in the Readiness Baseline (see Table 1). These projects have cost increases beyond $2.5 million and/or cost increases beyond 25 percent of the cost estimate.


 

Table 1
Project Cost Increases

Project Name

Current Cost

New Cost

Belmont- Community Path, Belmont Component of the MCRT (Phase 1)

$27,306,266

$48,934,961

+79.2%

 

Boston- Bridge Preservation, B-16-066 (38D), Cambridge Street over MBTA

$16,531,736

$20,741,786

+25.5%

 

Brookline- Rehabilitation of Washington Street

$27,959,721

$39,015,364

+39.5%

 

Lynn- Rehabilitation of Essex Street

$23,567,554

$33,813,139

+43.5%

 

Lynn- Rehabilitation of Western Avenue (Route 107)

$45,897,600

$68,189,552

+48.6%

 

MBTA = Massachusetts Bay Transportation Authority. MCRT = Massachusetts Central Rail Trail.

 

E. Lapointe stated that design consultant cost estimates do not always match MassDOT’s planning estimates. He gave an example of a project where contingencies, including engineering, design, and utility contingencies, made up more than 35 percent of the project cost estimate. Though contingencies generally decrease as design progresses, this is not always the case. Unexpected expenses may occur late in the design process, such as expenses for transit diversions or contaminated soil removal.

E. Lapointe stated that all five project cost increases are from projects that submitted design updates within the last six months (see Table 2). Often, long periods of time between design submissions correlate with significant cost increases. Three of these projects had not had a design milestone submission in five years or more.


 

Table 2
Cost Risk as a Factor of Time

Project Name

Design (FFYs 202731 TIP)

Design (FFYs 202630 TIP)

Time Difference (Years)

Belmont- Community Path, Belmont Component of the MCRT (Phase 1)

100% Comments to DE (01/15/2026)

75% Submitted (03/06/2025)

0.86

 

Boston- Bridge Preservation, B-16-066 (38D), Cambridge Street over MBTA

25% Received (10/14/2025)

PRC Approved (12/21/2022)

2.81

 

Brookline- Rehabilitation of Washington Street

25% Comments to DE (01/27/2026)

PRC Approved (09/24/2020)

5.35

 

Lynn- Rehabilitation of Essex Street

25% Received (09/24/2025)

PRC Approved (12/06/2018)

6.81

 

Lynn- Rehabilitation of Western Avenue (Route 107)

25% Comments to DE (12/02/2025)

PRC Approved (12/06/2018)

6.99

 

DE = District Engineer. MBTA = Massachusetts Bay Transportation Authority. MCRT = Massachusetts Central Rail Trail. PRC = Project Review Committee.

 

E. Lapointe stated that the MPO’s readiness guidelines require cost updates no less than once every 1.5 years. The majority of projects abide by this guideline, but there are several projects that have not had a cost update in over four years.

E. Lapointe noted that the MPO board retains the prerogative to consider making exceptions to the readiness policy, but only for projects that are designated as low risk for their advertising year. A low-risk project has a simple scope of work, minimal right-of-way easements and required permits, and at least a 25 percent design submission.

Discussion

B. Rawson commented that the work done by the MPO is bearing results in the forms of better information flow and reduced project risk.

Lenard Diggins (Town of Arlington) asked if it is clear whether or not cost contingencies have been factored into a project’s cost.

E. Lapointe answered that it is because of better information flow between the MPO and MassDOT and the requirements of the readiness policy.

E. Chute stated that the Town of Brookline underwent an extensive year-long public community process for the Washington Street project. When the Town was preparing the 25 percent design for submission, MassDOT’s requirements changed, and the Town was required to submit the subsurface utilities plan as part of the 25 percent design instead of the 75 percent design. This change delayed the 25 percent submission. She encouraged the committee to understand that late design submissions may happen for a multitude of reasons outside of the control of the municipal proponent. She stated that the Town’s consultant is not in agreement with MassDOT’s recent cost increase and encouraged the committee to reconcile the discrepancies between the MassDOT and consultant design estimates before this presentation is brought to the full board.

J. Rowe stated that the Subregional Readiness Days could be an opportunity to share information about discrepancies between cost estimates.

B. Rawson said that it might be useful to develop a dashboard or similar tool to have better transparency for project design statuses, such as whether an intersection control evaluation has taken place or if project requirements were changed during the project lifecycle.

E. Lapointe stated that the MPO must use the cost estimate recorded in MassDOT’s project information system. If the MassDOT estimate is lower than the consultant estimate, that discrepancy can be discussed between the proponents and the MassDOT staff. However, if the MassDOT estimate is higher than the consultant estimate, the MPO board cannot choose to fund the lower figure.

5.    FFYs 2027–2031 Program Development Objectives—Ethan Lapointe, MPO Staff

E. Lapointe stated that during the development of the FFYs 2025–29 and 2026–30 TIPs, the board spent the majority of the time working to attain fiscal constraint and allocated unprogrammed balances in earlier TIP years. MPO staff received feedback that there were insufficient time and information to make informed programming decisions; that there was inconsistent application of the MPO’s cost and readiness policies; and that there was confusion around the roles and responsibilities for TIP program development, especially regarding the role of the TIP Committee. The adoption of the readiness guidelines has mitigated some of these challenges. Although there is an approximately $20 million deficit in FFY 2030, there are strategies in place to address this issue through the MPO’s TIP Project Cost Policies.

E. Lapointe reminded the committee that four MPO board meetings are scheduled for TIP program development. The first was on February 19, 2026, when the Readiness Baseline was discussed. Next, initial modifications will be made during the March 5, 2026, meeting. On the March 19, 2026, meeting, the board will further refine the program and consider more complex factors. Lastly, the board will adopt the final program on April 2, 2026. The TIP Committee will meet on March 12, 2026, and March 26, 2026, to develop recommendations.

At the March 5, 2026, MPO board meeting, MPO staff will ask the board to consider making decisions on smaller projects, including design funding, Community Connections projects, smaller bikeshare projects, and smaller or returning transit projects. These are projects that are generally less than $5 million in cost and have programming years in FFY 2027 or 2028. Time permitting, MPO staff encourage the MPO board to address a potential FFY 2028 advertising year for the Boston Bridge Preservation, Cambridge Street over MBTA project due to its relatively simple project scope and the need to alleviate the deficit in FFY 2030. In addition, the board could address cost increases for Lynn’s Rehabilitation of Essex Street and Rehabilitation of Western Avenue projects, the Rehabilitation of Washington Street in Brookline, and the Boston bridge preservation project. Addressing these changes may resolve the FFY 2030 deficit without requiring further project delays.

On the March 19, 2026, MPO board meeting, MPO staff will ask the board to consider larger funding decisions in the earlier years of the TIP, including the cost increase of the Belmont Community Path project, transit projects, larger bikeshare projects, MassDOT fill-in projects, and more. There will be about $300 million worth of projects to choose from. Staff will present illustrative scenarios, or “bundles” of projects. Staff will also request the board to release TIP Amendment 3 to the FFYs 2026–30 TIP for public comment. This will include cost changes for projects programmed in FFY 2026, transit projects seeking funding in FFY 2026, delays from FFY 2026 to FFY 2027, and a $5 million Bluebikes expansion project.

At the April 2, 2026, MPO board meeting, the board may make any final programming decisions, including whether to program new municipal-proponent projects.

Discussion

B. Rawson asked if there would be a formal board vote regarding changes to the TIP program at the upcoming MPO board meetings.

E. Lapointe answered that he would defer to the board on whether or not there would be a formal vote.

L. Diggins asked for clarity as to what the MPO board expects from the TIP committee.

J. Rowe answered that there was no clear directive given, but that this could be discussed at an upcoming MPO board meeting.

Caitlin Allen-Connelly (Community Advisory Council) asked for clarification on the bundles of projects that MPO staff would be bringing forth.

E. Lapointe answered that at the March 5, 2026, meeting, MPO staff would present a bundle of projects less than $5 million each. Staff would defer to the board for larger projects.

Meghan Roche (Minuteman Advisory Group on Interlocal Coordination) asked what the available pool of money was for funding smaller projects.

E. Lapointe answered that MPO staff are only considering addressing projects less than $5 million, of which there are few. Even if the board decides to fund all of these projects, there would still be approximately $50 million of surplus in FFY 2026 alone.

B. Rawson asked for clarification on the Boston bridge preservation project’s recent cost increase and why it would be different enough in scope to warrant an exception to the readiness policy.

Preston Huckabee (Gill Engineering) answered that when the project was initiated in August of 2022, Gill Engineering expected to rehabilitate the structure in kind. Later, the project limits expanded to connect with another project in the Boston neighborhood of Lost Village. The scope incorporated more Complete Streets elements, including widened sidewalks and bicycle facilities. The design also accommodated an MBTA request for a left turn lane for buses to enter Sullivan Square. Lastly, the project needed to be coordinated with the Rutherford Square project. These elements all contributed to increases in cost. However, bridge preservation projects are typically designed faster than other typical TIP projects. There are only four temporary easements involved in the project, and the project is all within city-owned property. Gill Engineering will be submitting a combined 75/100 percent submission.

6.    FFYs 2027–2031 Program Development Objectives—Adriana Jacobsen, MPO Staff

A. Jacobsen presented the scores for projects applying for TIP funding this spring and the scores for projects that underwent rescoring (see Tables 3–6). She noted that at the upcoming MPO board meeting, the meeting materials would include a document with more detailed information about all of the projects applying for programming on the TIP.

Table 3
New Project Scores (Core Investment Programs)

 

Proponent

Project ID

Project Name

Score

Brookline

613683

Brookline- Pedestrian Bridge Replacement, B-27-017, Davis Path over MBTA

73.7

Cambridge

613568

Cambridge- New Bridge and Shared-Use Path Construction over Fitchburg Line at Danehy Park Connector

85.3

Concord

612870

Concord- Assabet River Multi-Use Trail and Bridge Construction

59.9

Everett

613685

Chelsea- Everett- Reconstruction of Vine Street and Third Street, from Chelsea Street to MBTA Station

67.1

Malden

613244

Malden – Broadway Reconstruction Everett to Melrose City Line

78

Marblehead

612947

Marblehead- Village Street Bridge Replacement M-04-001

44.4

Newton

613594

Needham- Newton- Bridge Replacement on Christina Street

74

Revere

S13406

Revere- Revere Beach Connector (Design Only)

71.4

 


 

Table 4
New Project Scores (Transit Transformation)

 

Proponent

Project ID

Project Name

Score

CATA

S13388

CATA Access for All

39.8

CATA

S13389

Cape Ann Dialysis Transportation

39.8

CATA

S13412

Magnolia Shuttle

28.6

CATA

S13413

Vehicle Replacement

21.6

MBTA

S13393

Symphony Station

50.6

MBTA

S13394

Downtown Crossing Vertical Transportation Improvements Phase 2

42.6

MBTA

S13402

High Priority Stations Accessibility Improvements Program

44.8

MBTA

S13406

Locomotive Procurement

41

MBTA

S13420

North Station Rapid Transit Flooring Replacement

36.8

MBTA

S13397

Franklin Line Double Track Improvements – Phase 3

43.6

MBTA

S13398

Unit Substation Upgrade/Replacement

45.4

MBTA

S13399

Haverhill Line Double Track Improvements

43.8

MBTA

S13395

Operational Enhancement of Bus Routes 714 and 716

34.8

MBTA

S13396

Bus Priority and Accessibility Improvements

53.6

MBTA

S13401

Better Bus Project – Operational Safety Improvements at Bus Stops

44.6

MBTA

S13404

Silver Line Tunnel Flood Mitigation

47.8

MBTA

S13405

Blue Line Tunnel Airport Flood Mitigation

51.6

MWRTA

S13390

Procurement of 10 Compressed Natural Gas (CNG) Vehicles

49.5

MWRTA

S13391

Construction of Vehicle Maintenance and Fueling Facility

55.6

MWRTA

S13392

Procurement of Hydrogen Fuel Cell-Powered Transit Vehicles

50.8

CATA = Cape Ann Transportation Authority. MBTA = Massachusetts Bay Transportation Authority. MWRTA = MetroWest Regional Transit Authority.


 

Table 5
New Project Scores (Community Connections and Bikeshare Support)

 

Proponent

Project ID

Project Name

Score

Brookline

S13386

Brookline Bluebikes Expansion

79.5

Brookline

S13387

Brookline Bicycle Rack Expansion

76.5

Malden

S13385

Malden Bicycle Rack Expansion

78

MAPC

S13411

Boston, Brookline, Cambridge, and Somerville Bluebikes Replacement of 58 Stations

81

MAPC

S13409

Joint Municipality Bluebikes Expansion, 1500 E-Bikes, 25 Classic

Bikes, 17 Stations

85

Quincy

S13410

Quincy Bluebikes Expansion

63

MAPC = Metropolitan Area Planning Council

 

Table 6
Rescored Projects

 

Proponent

Project ID

Project Name

Score

 

Boston

606226

Boston- Reconstruction of Rutherford Avenue, from City Square to Sullivan Square

69

 

Boston

606453

Boston- Improvements on Boylston Street

62

 

Everett

609257

Everett- Reconstruction of Beacham Street

57

Medford

611982

Medford- Shared Use Path Connection at the Route 28/Wellington Underpass

53

Lexington

S13146

Lexington- Design of the Reconstruction of the Interstate 95 and Route 4/225 Interchange

49.8

Lynnfield

613163

Lynnfield- Rail Trail Construction, from Ford Avenue to Nichols Lane

50

MassDOT

605857

Norwood- Intersection Improvements at Route 1 and University Avenue/Everett Street

34.7

MassDOT

605168

Hingham- Improvements on Route 3A

-

MassDOT

609531

Arlington- Stratton School Improvements

-

Woburn

610662

Woburn- Roadway and Intersection Improvements at Woburn Common

47.5

MassDOT = Massachusetts Department of Transportation

 

A. Jacobsen stated that detailed scoring results would be sent to project proponents shortly.

Discussion

B. Rawson asked if there would be a fill-in project list from MassDOT. He asked if any of the scored transit projects would be considered as fill-ins.

A. Jacobsen replied that many of the MBTA, CATA, and MWRTA projects have readiness years in FFY 2026 or 2027, as do several of the Community Connections and bikeshare projects.

E. Lapointe added that MPO staff are still working with MassDOT to identify programming years for MassDOT fill-in projects.  

L. Diggins asked if there was any information in writing from TIP Readiness Days. He requested more information on the reasons for cost increases or delays.

E. Lapointe replied that there was not, but pointed him to the TIP Project Descriptions that would be posted on the MPO meeting calendar for the March 5, 2026, MPO board meeting.

7.    Members’ Items

There were none.

8.    Next Meeting

The next meeting is scheduled for March 12, 2026.

9.    Adjourn

A motion to adjourn was made by the Town of Arlington (Lenard Diggins) and seconded by the Community Advisory Council (Caitlin Allen-Connelly). The motion carried.


 

Attendance

Members

Representatives

and Alternates

City of Boston

Jen Rowe

Inner Core Committee (City of Somerville)

Brad Rawson

Metropolitan Area Planning Council

-

Massachusetts Department of Transportation (MassDOT)

Sam Taylor

Massachusetts Department of Transportation (MassDOT)

Michael O’Dowd

MetroWest Regional Transit Authority (MWRTA)

Tyler Terrasi

MetroWest Regional Collaborative (City of Framingham)

Dennis Giombetti

Minuteman Advisory Group on Interlocal Coordination (Town of

Lexington)

Meghan Roche

Community Advisory Council

Caitlin Allen-Connelly

At-Large Town (Town of Arlington)

Lenard Diggins

At-Large Town (Town of Brookline)

Erin Chute

 

Other Attendees

Affiliation

Aleida Leza

-

Allison Lenk

-

Ben Sun

City of Boston

Benjamin Muller

MassDOT

James Turnbull

Gill Engineering

Jim Nee

MWRTA

Jim Tarr

City of Malden

John Romano

MassDOT

JR Frey

Town of Hingham

Justin Curewitz

Tighe & Bond

Karin Rose

City of Boston

Logan Casey

Town of Marblehead

Maura Carroll

-

Michael Trepanier

MassDOT

Nelson Mui

MWRTA

Preston Huckabee

Gill Engineering

Rich Kosian

-

Richard Azzalina

Stantec

Valerie Oorthuys

Town of Stow

 

MPO Staff/Central Transportation Planning Staff

Tegin Teich, Executive Director

Annette Demchur

Dave Hong

Ethan Lapointe

Ibbu Quraishi

Lauren Magee

Sean Rourke

 


 

CIVIL RIGHTS NOTICE TO THE PUBLIC

Welcome. Bem Vinda. Bienvenido. Akeyi. 欢迎. 歡迎.

 

You are invited to participate in our transportation planning process, free from discrimination. The Boston Region Metropolitan Planning Organization (MPO) is committed to nondiscrimination in all activities and complies with Title VI of the Civil Rights Act of 1964, which prohibits discrimination on the basis of race, color, or national origin (including limited English proficiency). Related federal and state nondiscrimination laws prohibit discrimination on the basis of age, sex, disability, and additional protected characteristics.

 

For additional information or to file a civil rights complaint, visit www.bostonmpo.org/mpo_non_discrimination.

 

To request accommodations at meetings (such as assistive listening devices, materials in accessible formats and languages other than English, and interpreters in American Sign Language and other languages) or if you need this information in another language, please contact:

 

Boston Region MPO Title VI Specialist

10 Park Plaza, Suite 2150

Boston, MA 02116

Phone: 857.702.3700

Email: civilrights@ctps.org

 

For people with hearing or speaking difficulties, connect through the state MassRelay service, www.mass.gov/massrelay. Please allow at least five business days for your request to be fulfilled.